Mass.gov  
Office Of Transporation Planning Massachusetts Department of Transporation
ENVIRONMENTAL REVIEW
  


The South Coast Rail project must go through an in-depth analysis to evaluate the impact of the project on the natural environment and historic resources in order to obtain the permits needed to build the project.  There are two processes – one at the state level called the Massachusetts Environmental Policy Act and one at the federal level called the National Environmental Policy Act. 

Restoring rail service to the South Coast region has been extensively studied for almost twenty years. In 2002, a state-level environmental review recommended one particular route. However, the lead federal agency regulating the project, the U.S. Army Corps of Engineers, was not part of that review process.  In order to obtain a Clean Water Act permit under federal law, MassDOT needs to run the project through the Corps’ methodology which required looking at the alternatives again. The 2002 data is out-of-date now, so MassDOT consolidated this federal review with an updated state review.  The goal of this joint review is to identify the route and type of transportation (rail, bus, etc.) that results in the least harm to the environment while still serving enough people to make the project worthwhile. 

The project has combined the state and federal review into a joint review with two phases:


  • Phase 1.  The first phase of a joint federal-state process convened all the state and federal environmental agencies that have a say in the project’s design.  MassDOT asked the agencies and the public to suggest different alternatives for building the project and ways to evaluate the options against one another.  Sixty-five alternatives were proposed along with almost forty evaluation criteria.  This phase was completed in April 2008, and a smaller set of alternatives were advanced to the second phase of review for rigorous study. 

  • Phase 2.  The state and federal documents that kicked off this second phase, the formal review process, were the Environmental Notification Form/ENF and the federal Notice of Intent/NOI.  These documents were filed in November 2008.  The Commonwealth issued a scope of work including alternatives to be studied in April 2009.  The project team is analyzing these alternatives in detail and has provided to environmental regulators 5,000 pages of technical data on the impacts of the project, how the service will operate, what the travel time will be, and where the stations will be located.  The U.S. Army Corps of Engineers is preparing the federal Draft Environmental Impact Statement (DEIS) based on this data. The state version of this document, the Draft Environmental Impact Report (DEIR), will be combined with the DEIS to make public review easier.  The Army Corps of Engineers has indicated that it will take about seven months to complete the document, which will likely mean a late spring 2010 release for public review, although this schedule is subject to change by the Corps.

MassDOT Home | About Us | Employment | Contact Us | Site Policies Copyright © 2012 Commonwealth of Massachusetts